ASM Thame Site Developments

A historical page from when we developed our Thame site in 2007.

The now fully up-and-running site enables us to achieve huge operational efficiencies by being able to co-ordinate all of our following activities on one ‘state-of-the-art’ site:

This new ‘one-stop-shop’ re-development represents a significant step forward for ASM's auto recycling operation, and we are sure that ultimately – and most importantly – it is our customers who will reap the many benefits that have come about as a result of the new site's synergies.


10th April 2007 - At last, demolition of the old buildings begins.


 

11th June 2007 - The first steel uprights are put in place.


 

28th June 2007 - The new Parts Shop is starting to take shape.....what a difference a couple of weeks makes!


 

20th July 2007 - Given the rain, we're getting there slowly but surely.


 

31st August 2007 - hopefully, we're only six weeks away from completion.


 

12th October 2007 - still about one month to go...but it's looking great!


 

1st November 2007 - six vehicle technicians' workshop ramps are in.


 

26th November 2007 - one week to go ... hopefully !!!